All india level Je/AE Questions Quiz- 6
1.The percentage of earnest money isA. 1%B. 2%C. 5%D. 10%Answer :- While submitting a tender the contractor is to deposit a certain amount, approximately about 2% of the estimated cost with the department as the guarantee of the tender is called as earnest money. 2.The percentage of security money is aboutA. 2%B. 5%C. 10%D. 15%Answer :- If the contractor accepted the tender , then he has to deposit 10% of tendered amount as security money with the department which is inclusive of the earnest money already deposited. 3.The unit of measurement of supply of coal isA. Cubic metresB. Sq m.C.