Nwda Je Civil Previous Years Questions Paper’s Quizes -8
1.Out turn work is the quantity of work which can be done by an artisan for trade working of ( hours )A. 8B. 10C. 12D. 14Answer :- Out turn work is the quantity of work which can be done by an artisan for trade working of 8 hours. 2.The measurement of painting letters and figures is done inA. Sq.m.B. NumberC. Cu.m.D. Running meterAnswer :-1.The measurement of removing paint or varnish is done in Sq.m.2.The measurement of painting letters and figures is done in number.3.The measurement of polishing of wood work is done in sq.m. 3.The Asbestos cement corrugated sheet is
The post Nwda Je Civil Previous Years Questions Paper’s Quizes -8 appeared first on Exam Guru g.